Cranston Second Elementary School
66 Cranford Drive SE
Anticipated Opening Date | September 2020
Grades | K-4
Mar. 19, 2019
Bird Construction has mobilized to site and construction will be getting underway. The Site Plan on the right-hand side of this page shows the footprint of the school on the site.
Construction Status
The construction status is updated using the Construction Projects Status Report.
May 2019
Design and specifications |
100% |
Construction Award |
100% |
Construction Progress
|
1% |
Note: Project managed by Alberta Infrastructure. Contractor mobilized to site March 2019. Erosion and sedimentation control and site preparation underway. |
|
Feb. 2019
Design and specifications |
100% |
Construction Award |
100% |
Construction Progress
|
0% |
Note: Project managed by Alberta Infrastructure. Contractor anticipated to mobilize to site in February 2019. |
|